Construction is tentatively scheduled to begin in Spring 2019 for I-294/I-57 Interchange Project – Phase 2.
Phase 2 includes:
Median work on I-57 north of I-294
Ramp pavement
Reconstruction of I-57/147th Toll Plaza
Installation of retaining walls
Construction of a flyover ramp on I-294/I-57/Dixie Creek
Construction of southbound and northbound CSX Railroad bridges
All work will be coordinated with the Illinois Department of Transportation and local communities. The project is expected to be complete by 2022.